Homeowner guides · November 11, 2026

Plumbing and sprinkler rough in inspection in Anne Arundel County: the checklist before drywall.

A new house in Anne Arundel County needs two rough in inspections passed before insulation and drywall: the plumbing rough in and the sprinkler rough in. The permit holder requests both through the county’s Land Use Navigator. Both need the pipe exposed, and the stamped plans have to be on site. Cover the pipe early and the wall comes back open.

The county has required fire sprinklers in new one and two family homes and townhomes since 2009, so almost every new house from Glen Burnie to Edgewater gets both visits. Owner builders and first time general contractors miss the second one more than any other inspection on the permit. If you are still sorting out which inspector signs for what, start with our guide to the residential plumbing inspection in Anne Arundel County.

What inspections does a new house need before drywall in Anne Arundel County?

A house on a slab needs the plumbing ground inspection first, then the plumbing rough in and the sprinkler rough in once the framing is up. Gas piping adds one more. The county publishes each inspection with a number in its inspection types directory, and that number is what you pick when you make the request.

InspectionCounty codeListed underWhat the inspector is there to see
Ground410PlumbingDrain and supply pipe under the slab, before the pour
Gas rough in420PlumbingGas piping in open walls
Plumbing rough in425PlumbingSupply, drain and vent pipe in open walls and ceilings
Sprinkler rough in290BuildingSprinkler pipe, hangers and head locations, before drywall
Plumbing final499PlumbingFixtures set and working
Sprinkler final295BuildingHeads in, valve open, water flowing at the test connection

The two finals are in the table so you can see the whole path. The county will not schedule the final building inspection until the trade permits tied to it have passed their own finals.

How do I schedule a rough in inspection in Anne Arundel County?

You request it online in the Land Use Navigator, or by phone through the county dispatcher at (410) 222-7784, weekdays from 7:30 a.m. to 4:00 p.m. The county’s trade inspections page puts the job on the permit holder. No inspector shows up because the framing looks ready. Three rules from that page catch people:

  1. The permit has to be active for 24 hours before you can request the first inspection.
  2. Approved construction drawings have to be on site.
  3. A re-inspection fee is charged when the work is not ready or a violation was not corrected.

The Fire Marshal Division asks for at least three working days of notice on the inspections it runs, so book the sprinkler visit before the drywall delivery date is set. An address inside the City of Annapolis goes through the city’s own permit office and fire marshal. The steps for both offices are in our Anne Arundel County fire sprinkler permit guide.

What does the inspector need to see at the sprinkler rough in?

The inspector needs to see every foot of sprinkler pipe, open and unpainted, matching the approved drawings. Walk the house the day before with this list:

  1. Stamped plans on site. The approved sprinkler drawings, with the county review stamp. Copies without the stamp do not count.
  2. Nothing covered. No insulation, drywall or paint over any CPVC or PEX sprinkler pipe. That includes the garage ceiling and the attic runs.
  3. Pipe hung the way it was drawn. Routing, hanger spacing and head locations match the plan. A head moved to dodge a relocated beam needs a revised drawing first.
  4. System holding pressure. The pipe is filled and tight with no weeping joints. We check which test pressure the office wants on your job before the visit.
  5. Head count right. Heads usually go in after paint, so the inspector sees plugs. The number of outlets and where they sit still have to match.
  6. Well equipment placed. On a south county lot with a private well, the stored water tank and booster pump are where the drawings show them.

Which goes first, the plumbing rough in or the sprinkler rough in?

Either can go first. What matters is that both pass before insulation. On a standalone system with its own orange CPVC pipe, the two inspectors look at different pipe and the order makes no difference. On a multipurpose system the sprinkler heads feed off the same PEX as the faucets, so both inspectors read the same pipe. Book those two visits close together, and keep the plumber from closing a chase the sprinkler inspector still needs open. Our guide to multipurpose vs standalone systems shows how to tell which one is in your walls.

The same order holds on every new house in the county. Home fire sprinklers in Anne Arundel County covers how we work there, and fire sprinkler installation for new homes in Anne Arundel County covers the build from plan to final.

What fails a rough in inspection?

Four things account for most failed first visits on the sprinkler side:

The Fire Marshal Division’s contractor’s guide says a $100 reinspection fee may be charged after a failed inspection, and it has to be paid before the next visit is scheduled. The fee is the small part. The real cost is the days the drywall crew sits idle, or the ceiling you cut back open to show a hanger.

Can my plumber handle the sprinkler rough in too?

No. Sprinkler pipe in Maryland is installed under a fire protection contractor license from the State Fire Marshal, and a plumbing license does not cover it. The plumber calls for the plumbing rough in. We get the sprinkler side ready for that visit. The longer answer is in whether a plumber can work on fire sprinklers in Maryland.

What does the sprinkler side of the permit cost?

A new construction 13D system on public water runs about $1.35 to $1.60 per sprinklered square foot, with the rough in and the acceptance test in that price. A well lot adds $3,000 to $6,000 for the stored water tank and booster pump. Those figures are from our published cost page. Every floor plan is different, so the number for your house comes from a call with the drawings in hand.

Framing up and no sprinkler contractor yet?

Send the address, the square footage and where the build stands. You get a written quote against published pricing, and a straight answer on what has to happen before drywall.